In the Cost of Power in Large-Scale Data Centers, we looked at where the money goes in a large scale data center. Here I’m taking similar assumptions and computing the Annual Cost of Power including all the infrastructure as well as the utility charge. I define the fully burdened cost of power to be the sum of 1) the cost of the power from the utility, 2) the cost of the infrastructure that delivers that power, and 3) the cost of the infrastructure that gets the heat from dissipating the power back out of the building.
We take the monthly cost of the power and cooling infrastructure assuming a 15 year amortization cycle and 5% annual cost of money billed annually divided by the overall data center critical load to get the annual infrastructure cost per watt. The fully burdened cost of power is the cost of consuming 1W for an entire year and includes the infrastructure power and cooling and the power consumed. Essentially it’s the cost of all the infrastructure except the cost of the data center shell (the building). From Intense Computing or In Tents Computing, we know that 82% of the cost of the entire data center is power delivery and cooling. So taking the entire monthly facility cost divided by the facility critical load * 82% is an good estimator of the infrastructure cost of power.
The fully burdened cost of power is useful for a variety of reasons but here’s two: 1) current generation servers get more work done per joule than older serves -- when is it cost effective to replace them? And 2) SSDs consume much less power than HDDs --how much can I save in power over three years by moving to using SSDs and is it worth doing?
We’ll come back to those two examples after we work through what power costs annually. In this model, like the last one (http://perspectives.mvdirona.com/2008/11/28/CostOfPowerInLargeScaleDataCenters.aspx), we’ll assume a 15MW data center that was built at a cost of $200M and runs at a PUE of 1.7. This is better than most, but not particularly innovative.
Should I Replace Old Servers?
Let’s say we have 500 servers, each of which can process 200 application operations/second. These servers are about 4 years old and consume 350W each. A new server has been benchmarked to process 250 operations/second, and each of these servers costs $1,3000 and consumes 165W at full load. Should we replace the farm?
Using the new server, we only need 400 servers to do the work of the previous 500 (500*200/250). The new server farm consumes less power. The savings are $111kw ((500*350)-(400*160)). Let’s assume a plan to keep the new servers for three years. We save 111kw each year for three years and we know from the above model that we are paying $2.12/kw/year. Over three years, we’ll save $705,960. The new servers will cost $520,000 so, by recycling the old servers and buying new ones we can save $185,960. To be fair, we should accept a charge to recycle the old ones and we need to model the cost of money to spend $520k in capital. We ignore the recycling costs and use a 5% cost of money to model the impact of the capital cost of the servers. Using a 5% cost of money over three years amortization period, we’ll have another $52,845 in interest if we were to borrow to buy these servers or just in recognition that tying up capital has a cost.
Accepting this $52k charge for tying up capital, it’s still a gain of $135k to recycle the old servers and buy new ones. In this case, we should replace the servers.
What is an SSD Worth?
Let’s look at the second example of the two I brought up above. Let’s say I can replace 10 disk drives with a single SSD. If the workload is not capacity bound and is I/O intensive, this can be the case (see When SSDs Make Sense in Server Applications). Each HDD consumes roughly 10W whereas the SSD only consumes 2.5W. Replacing these 10 HDD with a single SSD could save 97.5W/year and, over a three year life. That’s a savings of 292.5W. Using the fully burdened cost of power from the above model, we could save $620 (292.5W*$2.12) on power alone. Let’s say the disk drives are $160 each and will last three years, what’s the break-even point where the SSD is a win assuming the performance is adequate and we ignoring other factors such as lifetime and service? We’ll take the cost of the 10 disks and add in the cost of power saved to see what we could afford to pay for an SSD – the breakeven point (10*160+620 => $2220). If the SSD is under $2220, then it is a win. The Intel X-25E has a street price of around $700 the last time I checked and, in many application workloads, it will easily replace 10 disks. Our conclusion is that, in this case with these assumptions, the SSD looks like the better investment than 10 disks.
When you factor in the fully burdened price of power, savings can add up quickly. Compute your fully burdened cost of power (the spread sheet<JRH>) and figure out when you should be recycling old servers or considering lower power components.
If you are interested in tuning the assumptions to more closely match your current costs, here it is: PowerCost.xlsx (11.27 KB).
--jrh
James Hamilton, Data Center FuturesBldg 99/2428, One Microsoft Way, Redmond, Washington, 98052 W:+1(425)703-9972 | C:+1(206)910-4692 | H:+1(206)201-1859 | JamesRH@microsoft.com
H:mvdirona.com | W:research.microsoft.com/~jamesrh | blog:http://perspectives.mvdirona.com
Disclaimer: The opinions expressed here are my own and do not necessarily represent those of current or past employers.